Proposed Implementation Roadmap

DRAFT ONLY

This Plan is currently only a DRAFT and has not been accepted or implemented by WICEN WA. It is largely incomplete.

Why this page exists

Committee Discussion raises ten clusters of open questions — some are gaps in the plan itself, others are genuinely new capability proposals (community welfare messaging, a non-ham mobile repeater, ad-hoc satellite internet, permanent AREDN siting). Not all of it is achievable at once. WICEN WA is currently in a rebuilding phase, and most of what’s been discussed assumes a membership, budget, and equipment base the organisation doesn’t have yet.

This page is an assessment of relative cost and effort against that reality, and a proposed phased sequence — a recommendation for the committee to confirm, amend, or reject, not a decision that’s already been made.

Working assumption this roadmap depends on: it assumes Committee Discussion Section 1 gets answered as “build reliable local/regional capability first, state-wide capability later,” because that’s what current membership and activity level actually supports. If the committee decides the opposite — state-wide capability is the immediate priority — this sequencing needs to be rebuilt around that instead, not just relabelled.

Assessment

Proposal Capital cost Ongoing cost Regulatory / admin load Nature of the work Depends on
Inventory existing standing infrastructure (APRS digipeaters, MeshCore coverage) None None None — possibly a relationship if run by another club Documentation only; it already exists Nothing — can start immediately
Close existing domain gaps (PACE triggers, distinguishability issues, undefined tiers) None None None Documentation only Aims answered (Discussion §1, §3)
Local/Tactical Field Comms doctrine + Self-Assessment update Low regardless of technology chosen (APRS messaging costs nothing new; a mesh system is cheap per node) None None Mostly documentation; APRS capability already exists in members Local/Tactical confirmed as a near-term priority; technology chosen (Discussion §8)
Community welfare messaging pilot None to low — reuses existing Long-Haul HF digital skills None One relationship to build (Red Cross WA) Mostly documentation + one partnership conversation Long-Haul domain reasonably mature; Discussion §6 decision
Ad-hoc satellite internet — single-unit trial Moderate (one kit) Moderate, subscription-based, pausable Low Genuinely new capability Discussion §7 identity question; a real operational trigger to test it against
Mobile repeater for non-ham distribution High (repeater hardware + radios to distribute) High (ACMA apparatus licence, ongoing) High (spectrum licensing, plus who’s accountable for community-held radios) Genuinely new capability, significant Larger membership/budget, likely external co-funding
Permanent AREDN network in major centres High (hardware at multiple sites) High (site agreements, ongoing maintenance per node) Moderate (site negotiation, no spectrum licensing) Genuinely new standing infrastructure, significant Larger membership/budget; someone accountable for node uptime (Discussion §10)
Cross-State Coordination maturity Low equipment cost None None Mostly relationship-building over time WA-internal domains stable first; larger membership

The pattern in this table is the basis for the phasing below: documentation-only work costs nothing and should happen regardless of capacity; genuinely new capabilities should be ordered by capital cost, ascending.

Proposed phases

Phase 0 — Decisions (cost: committee time only)

Work through Committee Discussion Sections 1–10. Nothing below can be honestly sequenced until Section 1 (Mission & Scope) and Section 3 (Domain priority) are answered — everything here already assumes a specific answer to both, and that assumption needs to be confirmed, not inherited from this page.

Phase 1 — Close documentation gaps, and inventory what already exists

Define the PACE triggers, resolve the Activation & Alerting distinguishability gap, and fill (or explicitly mark as “not provided, by decision”) the missing Contingency/Emergency tiers in Long-Haul Message Traffic and Cross-State Coordination. Alongside that, inventory the standing infrastructure WICEN WA already has informal access to but hasn’t documented — South West WA’s APRS digipeater network and the expanding MeshCore coverage area (Discussion §10). Neither task needs equipment, new members, or budget; both are achievable at current capacity and shouldn’t wait for anything else. Knowing what’s already there also directly informs Phase 2 below.

Phase 2 — Local/Tactical Field Comms

Discussion §8 splits this into two independent layers rather than one technology choice: a community intake layer (MeshCore and/or UHF CB, for non-hams to get a message in) and an operator-to-operator layer (APRS messaging and/or AREDN, between licensed members). They don’t have to land together. The operator layer is the cheaper and more natural starting point — APRS messaging costs nothing new to acquire since members are already partly trained on it per the Capability Self-Assessment — and can proceed on its own timeline from the intake layer, which is more of a community-engagement decision than an equipment one. Once the committee has confirmed which layer(s) to build first, write the local-tactical-comms.md doctrine page and extend the Capability Self-Assessment to cover whichever is chosen.

Phase 3 — Community welfare messaging pilot

Once Local/Tactical is stable, this is mostly a matter of defining an intake model (doorknock/warden vs. a public drop-off point) and having one conversation with Red Cross WA about feeding into Register.Find.Reunite. It reuses skills and infrastructure WICEN already has in the Long-Haul domain rather than requiring new equipment.

Phase 4 — Satellite internet, single-unit trial

Don’t start with a fleet. One kit, trialled at a real event or exercise, tests both the operational value and whether it belongs in WICEN’s identity at all before committing further budget. Subscription-based cost is easier to pause or cancel than a fixed capital project if it doesn’t prove out.

Phase 5 — Larger standing capital investments: mobile repeater and permanent AREDN siting

The most expensive and highest-admin-load items on this list, and the two that most depend on WICEN WA no longer being in a rebuilding phase. Both are genuinely new standing commitments — not portable kit — with ongoing maintenance and accountability questions attached, so it’s worth considering them together rather than in isolation. Worth exploring co-funding or partnership with a served agency (DFES, SES, local government) rather than assuming WICEN self-funds either alone — the ACMA licensing, site agreements, and ongoing uptime accountability arguably belong to whoever benefits most from the coverage, not solely to WICEN.

Phase 6 — Cross-State Coordination maturity

Lowest equipment cost on the list but a genuinely slow one — interstate relationships take time to build regardless of budget. Only worth active investment once the WA-internal domains (Strategic Coordination, Local/Tactical) are solid; there’s little point coordinating interstate before WICEN WA can reliably coordinate with itself.

What would change this order

This sequencing isn’t fixed. Some things that would reasonably reorder it:

  • A served agency or local government offering to co-fund the mobile repeater or satellite kit would justify moving Phase 4 or 5 earlier — the cost assessment above assumes WICEN pays for it alone.
  • If membership doesn’t grow over the next 12–24 months, Phases 4–6 should be dropped from the plan rather than left “delayed” indefinitely — an aspiration with no realistic path to resourcing isn’t a plan.
  • If the committee’s answer to Discussion §1 is state-wide capability first, this entire ordering needs to be rebuilt around Strategic Coordination and Long-Haul Message Traffic maturity instead of Local/Tactical.

Outcome

This roadmap is a proposal, not policy. It should be brought to the committee alongside Committee Discussion for sign-off, amendment, or rejection — and revisited whenever the working assumption above is confirmed or overturned.